A clear view of your project.

Plan the work, review capacity and spending, and keep the decisions that matter in one practical Excel workbook.

Start with a copy. Keep the original blank workbook as your master. Save a separate copy for each project, and keep the completed example beside it while you learn the layout.

Your files

FilePurpose
project-desk-toolkit.xlsxThe blank workbook. Save a copy for each project.
project-desk-example.xlsxA completed fictional project showing how to enter information and read results.
Quick-Start.htmlThis guide. Open it in a browser or print it.
LICENSE.txtPermitted use and redistribution limits.

Your first 15 minutes

  1. Open the example, then the blank toolkit. Extract the ZIP before opening files. Use Microsoft 365 Excel for Windows. Review the example's Overview and a few rows on each working tab.
  2. Set up the project on Overview. Enter your project name in C5, reporting date in C6, timeline-start Monday in C7 and currency label in C8. The currency label is for presentation; the workbook does not convert exchange rates.
  3. Add the work on Plan. Enter task names, owners, start dates, finish dates and progress. Keep dates as Excel dates. The weekly timeline shows when a task overlaps a week; it does not schedule dependencies for you.
  4. Enter capacity and budget assumptions. Record available and planned hours for each person and week in Capacity. Add planned and actual amounts in Budget. Capacity allocations are maintained separately from task dates.
  5. Record risks and changes. Use Risks for risks, issues and decisions. Use Changes for proposed or approved scope changes. Keep projected effects separate from approved changes.
  6. Review Overview and save a dated copy. Check the reporting date, overdue work, capacity, budget and open items before sharing a status update. Use Excel's Print Preview when exporting a report to PDF.

How the tabs work together

TabWhat you maintainWhat to expect
OverviewProject setup and reporting controls.A summary of the work, capacity, budget, risks and changes entered in the working tabs.
PlanTask details, owners, dates and progress.A weekly Gantt view and status calculations. Task dates remain your responsibility.
CapacityAvailable hours and planned allocation by person and week.Visibility into unused capacity and overload. It does not infer effort from the task schedule.
BudgetBudget lines with planned and actual amounts.Totals and variances. Use one currency consistently throughout a project.
RisksRisks, issues and decisions, with ownership and follow-up.A structured record to review at project meetings. Risk scores support prioritization, not a guarantee of outcomes.
ChangesChange requests, approval status and estimated time/cost effects.Separate views of approved and pending effects. Approval does not automatically alter your baseline schedule or budget.
GuideReference only.Instructions and important limits kept with the workbook.

Prepared size

This version provides 150 task rows with a 26-week timeline, capacity planning for 10 people over 12 weeks, 100 budget lines, 50 risk/issue/decision records and 50 change requests. These are prepared workbook limits, not claims about automatic scheduling or live collaboration.

Keep the workbook dependable

Edit input cells

Follow the workbook's input legend. Formula areas contain calculated results. Paste values into input cells to avoid importing other files' styles or formulas.

Use the prepared area

Stay within the supplied rows and timeline. Adding rows or columns may require changes to formulas, validation, formatting and summary ranges.

Use consistent dates and units

Enter full dates, use hours for capacity, and keep one currency per workbook. Check progress entry against the field's percentage format.

Save useful checkpoints

Keep dated copies before a reporting cycle or major change. Formula calculations do not preserve a history of earlier inputs.

A simple weekly review

Common questions

Does it require macros, an account or a subscription?

The workbook is a local Excel file without macros or external data connections. You need your own compatible Excel license. It does not require an account with Project Desk.

Does it work in Google Sheets, Excel Online or on a Mac?

This release targets Microsoft 365 Excel for Windows. Other spreadsheet apps and platforms are not currently supported. Importing the file into another application can change formatting, validation or calculations.

Can the whole team edit it at once?

The download itself does not provide collaboration or access management. Shared editing depends on your Microsoft environment. Keep a single agreed working copy and a clear owner for updates.

Why does a weekly bar include only part of a task?

The Gantt view is a weekly overview. A highlighted week means that the task's date range overlaps that week. It is not an hourly schedule or a measure of hours worked.

Will approving a change automatically update the budget?

No. Changes record the decision and estimated effect. Update the baseline plan or budget yourself after approval and keep the prior version if you need a history. This prevents the same impact being silently counted twice.

Why is an expected result missing?

Check required inputs, date formats and whether a formula was overwritten. In Excel, set calculation to Automatic and recalculate. Compare your file with a fresh copy of the blank toolkit.

Can I request a customized version?

Custom development, data entry, project management and bespoke template changes are not included in this download.

How do I ask for help?

Use the support or seller-message channel on the platform where you purchased the toolkit. Include your order reference, Excel version, tab name and a screenshot or short description of the issue. Remove confidential project and personal information first.

What are the purchase and refund terms?

Check the terms shown by the sales platform before purchase. If a file is missing or defective, contact the seller through your order. Nothing in the product license limits rights that applicable law gives you.

Scope of the toolkit. This is a planning and reporting aid. It does not provide accounting, tax, legal or engineering advice; critical-path scheduling; automatic resource leveling; or an audit trail. Review outputs before making decisions.

Printing and pasted inputs

Overview prints the dashboard summary (B2:I17) on one landscape A4 page. Plan and the free Planner print the task register in columns A:L by default. The wide Gantt remains available on screen. To print a chosen timeline section, select that range and use Print Selection. Check the page range before printing: prepared blank rows are included.

Use dropdowns for statuses. Excel can bypass validation when values are pasted. Check pasted statuses, dates and percentages against the field rules, and review input-note warnings before relying on totals. The workbook does not block every invalid pasted value.